title: "Workday Sandbox Preview: 5-Week Release Testing Runbook"
description: "Week-by-week Workday Sandbox Preview testing schedule covering preview refresh, integrations, payroll parallel checks, security, and Production cutover."
url: https://kiweely.com/guides/workday-sandbox-preview-5-week-testing-schedule
---

# Workday Sandbox Preview Testing: A 5-Week Release Runbook

Follow a five-week Workday Sandbox Preview runbook from preview refresh and What’s New triage through integration testing, payroll parallel validation, security regression, and Production weekend cutover without breaking live HR, payroll, or downstream feeds.

-   **Checked** against Workday on November 24
-   Applies to **Workday Extend**
-   10 min read
-   Published November 24
-   By Kiweely

Workday releases major updates twice a year (R1 in spring and R2 in fall), giving every customer a fixed **five-week Sandbox Preview testing window** between the preview refresh and Production Go-Live. Treat those five weeks as a sequenced engineering runbook: triage **Automatically Available** changes and lock down non-production endpoints in Week 1, test core business processes and integrations in Week 2, run payroll parallel checks in Week 3, complete security regression and UAT in Week 4, and execute a controlled Production weekend cutover in Week 5.

Most release incidents happen for two avoidable reasons: teams spend the first two weeks reading release notes without touching Sandbox Preview, or they bundle optional opt-in features into the same cutover as mandatory release changes. Splitting mandatory regression from optional adoption keeps the five-week schedule predictable even for lean HRIS teams.

## The 5-week Sandbox Preview testing schedule at a glance

| Week | Primary Focus | Key Workday Tasks & Reports | Exit Gate | Primary Owners |
| --- | --- | --- | --- | --- |
|  **Pre-window (T-1)** | Freeze prep & endpoint inventory | Release Center review, integration endpoint audit | List of external SFTP/API endpoints to repoint after refresh | HRIS Lead, Integrations Lead |
|  **Week 1** | Refresh verification & impact triage | `What's New in Workday`, `Adoption Planning Dashboard`, `Process Monitor` | Signed-off mandatory regression list vs. deferred opt-in backlog | HRIS Lead, Functional Leads |
|  **Week 2** | Business processes, reports & integrations | Core BP smoke tests, `Integration Events`, EIB/Connector/Studio runs | Zero P1/P2 integration or BP failures; vendor test files verified | Integrations Lead, Functional Analysts |
|  **Week 3** | Payroll parallel & high-risk calculations | `Run Pay Calculation`, `Pay Calculation Results for Period`, `Create Payroll Accounting` | Gross-to-net and GL variances explained or logged with Workday Support | Payroll Lead, Finance Lead |
|  **Week 4** | Security regression, UAT & change comms | `Domain Security Policies for Functional Area`, `Start Proxy`, `Activate Pending Security Policy Changes` | Security sign-off, UAT sign-off, user job aids published | Security Admin, Business Owners |
|  **Week 5** | Go/No-Go, Production cutover & smoke check | Customer Central / Object Transporter cutover, post-release `Process Monitor` | Go-Live checklist complete; 48-hour integration watch clear | HRIS Lead, All Functional Leads |

## Pre-window prep (1 week before Preview refresh)

Workday publishes release documentation in the **Release Center** ahead of the Sandbox Preview refresh. Use the week before refresh to prevent Monday-morning surprises:

1.  **Snapshot in-flight work in Sandbox Preview.** Workday automatically refreshes Sandbox Preview with a copy of Production data at the start of the five-week window. Anything built only in Sandbox Preview and not migrated to Production or exported via Customer Central / Object Transporter is overwritten.
2.  **Inventory outbound integration endpoints.** Maintain a checklist of every integration that transmits files or API payloads to third parties (payroll providers, benefits carriers, banks, identity providers). You will verify these endpoints immediately after refresh so a test run cannot deliver preview data to a production vendor server.
3.  **Assign functional owners.** Map each enabled functional area (Core HCM, Recruiting, Benefits, Compensation, Time Tracking, Payroll, Financials, Security, Integrations) to one named tester and one backup.

## Week 1: Refresh verification and impact triage

Once the Sandbox Preview refresh completes, do not jump straight into feature testing. Verify tenant hygiene first, then narrow your scope to what actually affects your tenant.

### Day 1–2: Tenant hygiene and integration safety

-   Confirm the refresh timestamp and verify that Production data copied cleanly into Sandbox Preview.
-   Check scheduled future processes in `Process Monitor` and pause any recurring jobs that should not run unattended during testing.
-   Audit outbound integration delivery and retrieval attributes on critical EIBs, Core Connectors, and Workday Studio integrations. Confirm SFTP hosts, API URLs, and PGP keys point to vendor test environments rather than production endpoints.
-   Verify that testers have active accounts and appropriate proxy permissions in Sandbox Preview.

### Day 3–5: Run What’s New and split mandatory vs. opt-in scope

Run the standard **`What's New in Workday`** report directly inside Sandbox Preview (secured to the *Workday What’s New* domain under the System functional area). Filter it specifically to your footprint:

-   **Tenants:** `Preview`
-   **Enabled Functional Areas:** Select only the modules your organization actually uses
-   **Setup Effort:** Separate **Automatically Available** items from **Setup Required** items

Cross-reference the report with the **Release Center** on Workday Documentation, which categorizes notes into *Coming Soon*, *Feature*, *Fix*, and *Retirement*. Pay close attention to **Retirements** and **Fixes**—a retired web service operation, deprecated report data source, or altered default behavior can break an integration even if no new feature was turned on.

Log every **Automatically Available** item and relevant **Retirement** into your mandatory regression tracker. Move **Setup Required** items to a post-release adoption backlog unless leadership has already approved a specific feature for release weekend.

## Week 2: Business processes, integrations, and reporting

Week 2 is the heaviest execution week. Focus on end-to-end flows that touch multiple teams or external systems.

### Core business process smoke tests

Execute realistic transactions from start to finish rather than stopping at initiation:

-   **HCM lifecycle:** Hire (including pre-hire to worker conversion and onboarding steps), Job Change (promotion, transfer, manager change), Compensation Change, and Termination (checking downstream security revocation and benefit end dates).
-   **Employee and manager self-service:** Absence request and approval, time entry and approval, personal information edits, and direct deposit updates.
-   **Financials (if enabled):** Requisition to Purchase Order, Supplier Invoice approval, Expense Report submission, and Accounting Journal posting.

Check condition rules, routing steps, notifications, and completion steps on every process. Watch for subtle UI changes in Automatically Available updates that alter where managers click to approve or delegate tasks.

### Integration and custom report regression

-   **EIBs and Core Connectors:** Run outbound and inbound test cycles for Core Connector: Worker, Benefits connectors, and Payroll Interface / PECI integrations. Compare output files against a known-good Production baseline using a diff tool to spot shifted column headers, date formats, or missing XML elements.
-   **Workday Studio and Document Transformations:** Trigger end-to-end runs and inspect `Integration Events` and `View Background Process` for warnings, not just hard failures. Check whether any Studio assembly calls a Workday Web Service (WWS) version nearing deprecation.
-   **RaaS and custom reports:** Run high-traffic custom reports, composite reports, and BIRT layouts. Verify calculated fields still evaluate cleanly and that Report-as-a-Service (RaaS) endpoints return the expected JSON or XML schema for downstream BI tools.

## Week 3: Payroll parallel checks and high-risk calculations

If you run Workday Payroll (or feed an external payroll engine via PECI/PICOF), dedicate Week 3 to parallel validation. Waiting until Week 4 leaves no buffer if a variance requires a Workday Support case.

1.  **Pick a completed baseline pay period.** Select the most recent finalized Production pay period (ideally one that included retro pay, off-cycle adjustments, bonuses, or garnishments) so you have exact Production figures to compare against.
2.  **Recalculate in Sandbox Preview.** Execute `Run Pay Calculation` for the same pay group and period in Sandbox Preview, then pull `Pay Calculation Results for Period` and your standard payroll audit reports.
3.  **Diff gross-to-net and accounting lines.** Export summary and worker-level totals from both Production and Sandbox Preview. Compare gross pay, taxable wages, federal/state/local taxes, pre-tax and post-tax deductions, net pay, and `Create Payroll Accounting` journal outputs.
4.  **Classify every variance.**
    -   *Expected variance:* Statutory tax update or a documented fix in the Release Center.
    -   *Unexpected variance:* Altered custom calculation, changed time-to-payroll mapping, or modified rounding behavior.
5.  **Open Workday Support cases immediately.** Any confirmed release defect needs a documented reproduction case in Sandbox Preview by the end of Week 3 so Workday can evaluate or patch it before Go-Live.

## Week 4: Security regression, opt-in staging, and UAT

By Week 4, core transactions and payroll should be stable. Shift focus to access boundaries, approved opt-ins, and end-user readiness.

### Security regression checks

Workday releases occasionally introduce new securable items, split existing domains, or update delivered security policies.

-   Review `Domain Security Policies for Functional Area` and `Business Process Security Policies for Functional Area` for any domains referenced in your Week 1 `What's New in Workday` triage.
-   Check whether any pending security policy changes exist and verify what `Activate Pending Security Policy Changes` will commit.
-   Use `Start Proxy` to test at least five real personas: **Employee Self-Service**, **People Manager**, **HR Partner**, **Payroll Partner**, and a read-only **Auditor** role. Confirm each persona can still complete daily tasks and cannot view restricted compensation, health, or national ID fields.

### Opt-in staging and user communications

-   If you approved any **Setup Required** features for release weekend, finish configuring and testing them in Sandbox Preview now. Document every configuration object or package them through **Customer Central** and **Object Transporter** so you have a repeatable migration path.
-   Publish concise, role-specific release communications. Focus on what changes on Monday morning (new navigation paths, updated mobile or desktop layouts, changed approval screens) rather than listing backend fixes users never see.

## Week 5: Go/No-Go freeze, Production cutover, and post-release watch

Treat Week 5 as change control, not discovery.

### Monday–Wednesday: Defect closure and Go/No-Go

-   Re-test any fixes Workday delivered during the preview window (Workday updates preview tenants with fixes throughout the cycle).
-   Hold a 30-minute Go/No-Go meeting with HR, Payroll, Finance, Security, and IT leads. Confirm every open defect either has a verified workaround or is resolved.
-   Freeze non-emergency configuration changes in Production 24 to 48 hours before the release weekend so Production matches what you tested as closely as possible.

### Release weekend: Production cutover

-   Track the Workday release maintenance window until Production is back online.
-   Execute only the pre-approved cutover runbook: migrate staged packages via Customer Central / Object Transporter if applicable, enable approved opt-in toggles, and run `Activate Pending Security Policy Changes` if your checklist requires it.
-   Run a **read-only smoke test** before employees log in on Monday: verify SSO authentication, check home page announcements and dashboards, inspect `Process Monitor` for failed scheduled jobs, and confirm the first scheduled integration run succeeds.

### Post-release 48-hour watch

Monitor `Integration Events` closely for the first two business days after Go-Live. Some vendor-side issues only surface when a live production file reaches a partner’s production parser.

## Common Sandbox Preview failure modes

| Failure Mode | Why It Happens | How to Catch It Early |
| --- | --- | --- |
|  **Test data sent to a live vendor** | Sandbox Preview copies Production integration endpoints during refresh | Audit and repoint all outbound SFTP/API endpoints on Day 1 of Week 1 before running any integration |
|  **Silent downstream file breakage** | An Automatically Available field or XML change succeeds in Workday but fails in a vendor’s parser | Diff Sandbox Preview output files line-by-line against Production baselines in Week 2 |
|  **Missed security regressions** | Teams test only as a Security Administrator instead of real end-user roles | Run `Start Proxy` checks across Employee, Manager, HR, Payroll, and Auditor personas in Week 4 |
|  **Unexplained payroll variances** | Parallel testing is skipped or pushed to Week 5 when no time remains for Support triage | Run a full parallel pay calculation on a recent closed pay period in Week 3 |
|  **Cutover weekend overload** | Optional `Setup Required` features are bundled with mandatory release testing | Defer non-urgent opt-in features to post-release sprints and keep cutover strictly to mandatory items |

## What varies by tenant and agreement

Workday maintains a bi-annual major release cadence (R1 in spring and R2 in fall), with exact calendar dates, maintenance windows, and preview refresh weekends published in the Release Center each cycle. Your testing scope also depends on your licensed SKUs, enabled functional areas, country-specific payroll regulations, and whether you run Workday Financials or Extend alongside HCM. If you have custom integrations or Extend applications, budget extra time in Week 2 for API and schema validation.

## Where Kiweely fits

Running a disciplined five-week preview cycle twice a year takes repeatable checklists, cross-tenant diffs, and strict separation between Sandbox testing and Production changes:

-   **In-house HRIS teams** can use [Kiweely Nest](https://kiweely.com/nest) ($999/mo per seat; [book a demo](https://kiweely.com/demo?for=nest)) to run scheduled release routines across 11 specialist AI teammates—triaging `What's New` impacts, checking integrations and security boundaries in Sandbox Preview first, and gating any Production configuration change behind explicit human approval.
-   **Workday consultants and developers** supporting multiple client preview windows can use [Kiweely Vine](https://kiweely.com/vine) (free on a personal developer tenant, $99/mo Personal, $149/seat/mo Team) to inspect Studio integrations, XSLT transformations, custom reports, and Extend apps directly against preview tenants without manual copy-paste debugging.

## Frequently asked questions

### How long is the Workday Sandbox Preview testing window?

Workday delivers two major releases each year (R1 in spring and R2 in fall), and each release includes a five-week Sandbox Preview testing window. Workday refreshes Sandbox Preview with a copy of Production data at the start of the window so teams can test current configurations against upcoming release code before Production Go-Live.

### What is the difference between Automatically Available and Setup Required features in Workday releases?

Automatically Available features turn on in Production as soon as the release goes live and must be regression-tested during the five-week preview window. Setup Required (opt-in) features stay off until an administrator configures or enables them, so you can defer them to a later sprint instead of rushing them into cutover weekend.

### Can we skip payroll parallel testing if no payroll features changed?

No. Even when you opt out of new payroll features, underlying release fixes, tax engine updates, time-tracking changes, or calculated field adjustments can alter gross-to-net results or payroll accounting lines. Running at least one completed pay period in parallel catches silent variances before live payroll runs.

### Should we configure opt-in features in Sandbox Preview and migrate them to Production?

Stage and test only high-priority opt-in features in Sandbox Preview, and package approved changes via Customer Central and Object Transporter or a documented manual cutover checklist. Avoid bundling dozens of optional features into release weekend, because they make root-cause triage harder if an Automatically Available change causes a regression.

## Sources checked

-   [Workday Release Best Practices Guide](https://forms.workday.com/content/dam/web/sg/documents/other/release-best-practices-guide-en-sg.pdf)
-   [Workday Documentation: What's New in Workday Report](https://doc.workday.com/admin-guide/en-us/about-workday-documentation/about-workday-release-notes/concept--what-s-new-in-workday-report.html)
-   [Workday Documentation: Release Notes FAQ](https://doc.workday.com/admin-guide/en-us/about-workday-documentation/about-workday-release-notes/faq--release-notes-.html)
-   [Workday Documentation: Workday Tenants and Tools](https://doc.workday.com/workday-education/en-us/course-manuals/hcm-core-for-administrators/workday-tenants-and-tools.html)
-   [Workday Documentation: Customer Central](https://doc.workday.com/admin-guide/en-us/manage-workday/tenant-configuration/implementation-tools/customer-central/aci1574781562575.html)

## Related guides

[All guides](https://kiweely.com/guides)

### More guides on Tenants and developer accounts

[All 51 guides](https://kiweely.com/guides#tenants)

-   [Workday R1 and R2 Release Management: Auto-Enabled vs. Opt-In Triage](https://kiweely.com/guides/workday-release-management-auto-enabled-vs-opt-in-triage)
-   [Workday Retro Payroll: Calculation Triggers, NRPPT Limits, and Audit Procedures](https://kiweely.com/guides/workday-retro-payroll-calculation-triggers-audit)
-   [Workday Pay Groups, Run Categories, and Period Schedules: Setup Rules and Assignment Errors](https://kiweely.com/guides/workday-pay-group-run-category-period-schedule-setup)
-   [Workday Off-Cycle Payroll: On-Demand Payments, Manual Checks, Reversals, and Accounting](https://kiweely.com/guides/workday-off-cycle-payroll-on-demand-manual-check-reversal)
-   [Workday Garnishments and Withholding Orders: Priority Rules, Disposable Income, and Errors](https://kiweely.com/guides/workday-garnishments-withholding-orders-priority-errors)
-   [Workday 401(k) and Retirement Savings Plans: 2026 IRS Limits, Catch-Up Caps, and Employer Match Errors](https://kiweely.com/guides/workday-401k-retirement-contribution-limits-catch-up-errors)
-   [Workday Tenant Refresh and Data Masking/Scrambling: What Gets Wiped, PII Protection, and Post-Refresh Admin Checklist](https://kiweely.com/guides/workday-tenant-refresh-data-masking-scrambling-checklist)
-   [Workday Sandbox Preview Testing Calendar by Module: 5-Week Regression Plan](https://kiweely.com/guides/workday-sandbox-preview-testing-calendar-by-module)

### From the blog on Tenants and developer accounts

[All posts](https://kiweely.com/blog)

-   [How to Test a Workday MCP Connector in Claude or ChatGPT Using a Free Developer Tenant](https://kiweely.com/blog/testing-workday-mcp-connectors-on-free-developer-tenant)
-   [Designing Three-Button Workday Screens for Warehouse, Retail, and Healthcare Workers](https://kiweely.com/blog/simplifying-workday-for-frontline-warehouse-retail-healthcare)
-   [Designing Manager Time-Off and Timecard Approvals in Teams and Slack That Show Team Coverage](https://kiweely.com/blog/one-tap-workday-leave-and-timecard-approvals-in-chat)

## Your own AI Workday team, working from day one.

Kiweely Nest is coming next: eleven AI specialists for your company's Workday, and nothing changes in your tenant until you approve.

[Book a demo](https://kiweely.com/demo?for=nest) [See Kiweely Nest](https://kiweely.com/nest)

## Get the next guide in your inbox.

One email a month with new guides and one Extend tip. Nothing else.